Bridge steel formwork processing: How to control the deformation of steel formwork?
Bridge steel formwork processing: How to control the deformation of steel formwork?
source:Shandong Tianhong Heavy Industry Co., Ltd
Abstract:
The deformation control of steel formwork requires multidimensional technical intervention, and the specific measures and implementation standards are as follows:
1、 Design optimization measures
Stiffness Enhancement Design
The main ribs are made of 16 # I-beams with a spacing of ≤ 500mm, and the secondary ribs are densely arranged with 10 # channel steel with a cross-sectional modulus of ≥ 401.4cm ³
Pull screw diameter ≥ 16mm, spacing ≤ 450mm, pre tightening torque ≥ 200N · m
Pre deformation compensation
Pre set anti arch amount in the weld area (plate length L/800~L/1000)
Reserved expansion joints for the long side template, with compensation calculated at 0.015mm/(m ·℃)
2、 Construction process control
Strengthening the support system
Vertical spacing between poles ≤ 1.2m, horizontal spacing ≤ 1.5m, diagonal brace angle 45 °± 5 °
Foundation bearing capacity ≥ 150kPa, laying 20mm thick steel plate for stress diffusion
Dynamic Load Management
Layered pouring height ≤ 500mm, vibrating rod insertion spacing ≤ 400mm
Preloaded with 120% of the design load for 24 hours, with a deformation exceeding 2mm, immediately reinforced
Welding process control
Adopting jump welding technology, with each weld seam length ≤ 300mm and interlayer temperature ≤ 150 ℃
Welding current grading control (plate thickness 8mm: 130-170A, 10mm: 170-210A)
3、 Deformation correction technology
Applicable scenarios of correction method process parameters
Mechanical correction hydraulic jack applies pressure>1.2 σ s, local bending deformation ≤ 15mm
Flame correction linear heating temperature 650 ± 50 ℃ wave deformation/overall distortion
Cold work correction hammer impact energy ≤ 50J/cm ² angular deformation/joint misalignment
4、 Monitoring and acceptance
Real time monitoring indicators
Laser displacement sensor monitors template deflection, with a warning value set to L/500
Infrared thermal imager detects weld temperature gradient ≤ 80 ℃/m
Acceptance criteria
Plane position deviation ≤ ± 3mm, verticality ≤ 2mm/m
Joint gap ≤ 1.5mm, adjacent board height difference ≤ 1mm
Through the above control system, the deformation of steel formwork construction can be reduced by 60% -80%, and the qualification rate of concrete forming can be increased to over 98%.
Stiffness Enhancement Design
The main ribs are made of 16 # I-beams with a spacing of ≤ 500mm, and the secondary ribs are densely arranged with 10 # channel steel with a cross-sectional modulus of ≥ 401.4cm ³
Pull screw diameter ≥ 16mm, spacing ≤ 450mm, pre tightening torque ≥ 200N · m
Pre deformation compensation
Pre set anti arch amount in the weld area (plate length L/800~L/1000)
Reserved expansion joints for the long side template, with compensation calculated at 0.015mm/(m ·℃)
2、 Construction process control
Strengthening the support system
Vertical spacing between poles ≤ 1.2m, horizontal spacing ≤ 1.5m, diagonal brace angle 45 °± 5 °
Foundation bearing capacity ≥ 150kPa, laying 20mm thick steel plate for stress diffusion
Dynamic Load Management
Layered pouring height ≤ 500mm, vibrating rod insertion spacing ≤ 400mm
Preloaded with 120% of the design load for 24 hours, with a deformation exceeding 2mm, immediately reinforced
Welding process control
Adopting jump welding technology, with each weld seam length ≤ 300mm and interlayer temperature ≤ 150 ℃
Welding current grading control (plate thickness 8mm: 130-170A, 10mm: 170-210A)
3、 Deformation correction technology
Applicable scenarios of correction method process parameters
Mechanical correction hydraulic jack applies pressure>1.2 σ s, local bending deformation ≤ 15mm
Flame correction linear heating temperature 650 ± 50 ℃ wave deformation/overall distortion
Cold work correction hammer impact energy ≤ 50J/cm ² angular deformation/joint misalignment
4、 Monitoring and acceptance
Real time monitoring indicators
Laser displacement sensor monitors template deflection, with a warning value set to L/500
Infrared thermal imager detects weld temperature gradient ≤ 80 ℃/m
Acceptance criteria
Plane position deviation ≤ ± 3mm, verticality ≤ 2mm/m
Joint gap ≤ 1.5mm, adjacent board height difference ≤ 1mm
Through the above control system, the deformation of steel formwork construction can be reduced by 60% -80%, and the qualification rate of concrete forming can be increased to over 98%.
Disclaimer: The content provided on this website is for reference only (some information is sourced from the internet). The publication of content information is for the purpose of transmission and does not represent the views of this website. If the content involves copyright issues, please contact the website editor in a timely manner, and we will take appropriate measures to avoid unnecessary losses for both parties.
Related article
- Pulling out Mountains and Rivers for Win Win - Jining Tianli Employees Celebrate National Day Holiday with Tug of War Competition
- Customized specifications for steel formwork: What factors need to be considered in calculating the weight of steel formwork?
- Renting steel formwork manufacturers: How much does the material of steel formwork affect the price?
- Supplier of steel formwork rental station: How to deal with and prevent leakage of slurry in steel formwork?
- Steel template manufacturers supply for rent: How to deal with steel template size accuracy that is not up to standard? 双语对照 笔记
- How to calculate the bearing capacity of steel formwork for rental manufacturers of construction steel formwork?
- Nearby steel formwork rental station: How to deal with and prevent honeycomb and pockmarks on steel formwork?
- Composite bridge steel formwork processing manufacturer: How to check the dimensional accuracy after steel formwork correction?
- Composite steel formwork manufacturer supply: How to calculate the area of steel formwork?
- Customized processing of bridge steel formwork: how to prevent and deal with unstable formwork support?
- Steel formwork manufacturer supply specifications: What are the applicable fields for steel formwork
- Manufacturer of standardized steel formwork: How much impact does leakage of formwork joints have on structural safety?
Hot article

- Pulling out Mountains and Rivers for Win Win - Jining Tianli Employees Celebrate National Day Holiday with Tug of War Competition
- Pulling out Mountains and Rivers for Win Win - Jining Tianli Employees Celebrate National Day Holiday with Tug of War Competition
- Pulling out Mountains and Rivers for Win Win - Jining Tianli Employees Celebrate National Day Holiday with Tug of War Competition
- Pulling out Mountains and Rivers for Win Win - Jining Tianli Employees Celebrate National Day Holiday with Tug of War Competition
- Pulling out Mountains and Rivers for Win Win - Jining Tianli Employees Celebrate National Day Holiday with Tug of War Competition
- Pulling out Mountains and Rivers for Win Win - Jining Tianli Employees Celebrate National Day Holiday with Tug of War Competition
- 力“拔”山兮,“河”作共赢——济宁天力员工欢度国庆假期之拔河比赛
Recommended article

Customized rental of construction steel formwork: How to prevent and deal with loose joints in steel formwork?

Customized rental of steel formwork: What are the dimensions, specifications, and models of steel formwork?
- Customized rental of construction steel formwork: How to prevent and deal with loose joints in steel formwork?
- Customized rental of steel formwork: What are the dimensions, specifications, and models of steel formwork?
- Steel formwork manufacturer supply specifications: What are the applicable fields for steel formwork
- 力“拔”山兮,“河”作共赢——济宁天力员工欢度国庆假期之拔河比赛
- Pulling out Mountains and Rivers for Win Win - Jining Tianli Employees Celebrate National Day Holiday with Tug of War Competition
- Pulling out Mountains and Rivers for Win Win - Jining Tianli Employees Celebrate National Day Holiday with Tug of War Competition
- Pulling out Mountains and Rivers for Win Win - Jining Tianli Employees Celebrate National Day Holiday with Tug of War Competition
- Pulling out Mountains and Rivers for Win Win - Jining Tianli Employees Celebrate National Day Holiday with Tug of War Competition